To Jewish Autonomous Region discussed questions of a heat supply Birobidzhan

@RusGidro
Show original
Within a business trip across Far East the Chairman of the board – Director general Open joint-stock company "Federalnaya gidrogeneriruyushchaya kompaniya - RusHydro" Nicholas Shulginov carried out in Birobidzhan meeting on preparation of the Birobidzhan combined heat and power plant by forthcoming winter. During visit Nicholas Shulginov visited station and discussed a course of repair campaign with the management of Open joint-stock company "Dalnevostochnaya generiruyushchaya kompaniya" and the Birobidzhan combined heat and power plant.
Today at the Birobidzhan combined heat and power plant all maintenance of the equipment is complete by

one copper are carried out, by October capital repairs two more coppers will come to the end, the planned repair work on thermal networks of Open joint-stock company "Dalnevostochnaya generiruyushchaya kompaniya", proceeding from combined heat and power plant is finished.
"In 2018 financing repair and investment programs of the Birobidzhan combined heat and power plant we increased

proceeds of credit the return source for which while is not present", – Mikhail Shukaylov, director general Open joint-stock company "Dalnevostochnaya generiruyushchaya kompaniya" noted.

In February, 2018 between power engineering specialists and Government Jewish Autonomous region signed the Cooperation agreement in the sphere of increase of reliability of a heat supply of inhabitants Birobidzhan. In return Government Jewish Autonomous region promised to define sources of financings additional repair and investment programs of combined heat and power plant and to promote carrying out actions for increase energy efficiencies housing stocks and social objects Birobidzhan and to increase of reliability of municipal thermal networks, but a question with financing DGK expenses still is not solved. company is compelled to attract loans.

Summing up the results of meeting Nicholas Shulginov emphasized that preparation of the Birobidzhan combined heat and power plant for a heating season is under special control Open joint-stock company "Federalnaya gidrogeneriruyushchaya kompaniya - RusHydro". "Terms and volumes of the repair program are carried out, but also next year it is necessary to execute the same volume of repairs, to carry out capital repairs at least two coppers. The program is, and in a tariff or in budget the city we do not see the accounting of expenses on it. Is particularly acute a question and with payment discipline of consumers. Only the population of the city has a debt for thermal energy more than 300 million rubles. It actually sum of the two-year repair program of station. In 2019 capital and maintenance of combined heat and power plant it will be necessary to direct over 150 million more rubles on the program", – declared chapter Open joint-stock company "Federalnaya gidrogeneriruyushchaya kompaniya - RusHydro". At meeting discussion of need of development programs of complex modernization of combined heat and power plant, including heating systems, since 2023 and definition of its sources of financings also was carried out.