Works on Tomsk Kommunalny Bridge are complete for 91 percent

Show original
The deputy mayor Tomsk on architecture and to construction, Aleksey Aleksandrovich Makarov, carried out the next staff on repair Kommunalny Bridge. The press service of Administration of Tomsk. Following an order of the acting as the mayor Tomsk, Mikhail Ratner, full movement on both sides of the bridge was open at the beginning of September. Experts estimate readiness of works for 91%. At present in repair work it is involved 68 workers focused on implementation repairs under the bridge. Works on the 9th bridge footing are already performed. Besides, the contractor is engaged in coloring of a metalwork, repair...