the Modern substation "Nivenskaya" will provide to
JOINT-STOCK COMPANY "YANTARYENERGO", additional power will serve further development of economy Kaliningrad region.
"It is one of the first substations constructed and put into operation JOINT-STOCK COMPANY "YANTARYENERGO" for many years. It is sure that it will provide reliable Bagrationovsk district and will create opportunities for development of this territory" — the director general commented on JOINT-STOCK COMPANY "YANTARYENERGO" Igor Makovsky.
At construction of substation of power used the modern high-voltage equipment of the Russian production. So, on PS "Nivenskaya" two transformers on 16 megavolts-amperes made at JSC Tolyattinsky transformator plant LLC "Tolyattinsky Transformator" are installed. When developing configuration of substation the block and modular designs (BMD) of the open switchgear of 110 kV of also domestic production, allowing to reduce the square of substation at a third were applied.
For food of substation constructed an air-line of an electricity transmission of 110 kV from substation "Central" in the settlement Road 12 kilometers long, established 69 intermediate many-sided and 13 anchor trellised support of also Russian producers.