In ZhK "Monograph" under construction from Etalon Group works on the roof device] bega

Show original
Photo: Etalon group monolithic works on 13 sections of a housing estate, in the work closing stage on two remained sections are completely performed At the moment. Builders continue construction of internal walls and partitions in inhabited and technical rooms of buildings, 80% of designs are executed now. In an active phase of action for the structure of internal engineering systems: to laying sanitary and ventilating systems, storm sewerages and fire water supply systems, and also systems of power supply housing estate. Works on the roof device are performed. In parallel...