Dmitry Karasev: "Works go at full speed"

Show original
At present on object there is an arrangement of the pile base — the last, 14th well on the left coast (its depth of 45 subway) is drilled. In total 28 piles — on 14 on each of coast are spudded. "As soon as in December work on the left coast will come to the end, the contractor will begin the device of the pile base from 14 wells on the opposite. After the end of these works the device of beams and flying structures of the bridge" will begin — the town governor told. At present all works go according to the schedule, the only thing that can prevent — hard frosts, then it is necessary to draw up equipment...