The Tver power engineering specialists finished repair of the equipment one of Kashin's key feeding centers

Show original
Experts Branch of open joint-stock company "Interregional grid distribution company center" - "Tveryenergo" repaired the existing equipment of substation (PS) of 110/35/10 kV "Scope" in Kashin Tver Region. Works in the territory of the feeding center were conducted from May to September. Power engineering specialists executed repair two power transformers 25 MBA, the equipment of distributing devices of 110 kV, 35 kV and 10 kV, repaired 8 oil switches and 18 disconnectors, 29 cells with the equipment — switches, current transformers, tension transformers, transformers of own needs. Cosmetic repair buildings is also made...