The sociocultural center in Pazhge did not manage to complete in time

@BNK
Show original
In documents on construction found defects, and also additional works were required. In State Council of the Komi Republic considered the Culture state program. In the report of Control Audit Chamber of the region it is emphasized that on building of the sociocultural center in the village Pazhga Syktyvdinsky district are observed difficulties. For October readiness made 84% (according to actual data MINISTRY OF CULTURE, TOURISM AND ARCHIVING OF THE KOMI REPUBLIC already 92%), thus the date of completion of works expired on November 1. Lag from the schedule for 21 days as shortcomings in project documentation and need of additional works are revealed is observed. Acting Minister of Culture...