Where and why projects on rural water supply "hang" to Kostanay Region

Show original
The budgetary injections to this sphere grow, but means not completely accustom. There is an unfinished construction which cannot come to the end since 2021, was spoken on October 31 at meeting in regional akimat. At this design and estimate documentation becomes outdated, and construction materials for objects of water supply rise in price. If to compare with 2021, financing grew from 9,5 billion tenge to 15,3 billion tenge. Until the end of the year in areas 31 projects have to be complete, from them 8 new objects of water supply are already put into operation, the head of managements power engineering specialists and Household management company Askarov Dauren reported at meeting. In 39 villages or...