The kindergarten of lyceum Elektrogorsk is ready for 54%
In a kindergarten floors and walls are yet ready. Repair has to come to the end by the end of the year. The head of the Pavlovo-Posadsky lake Denise Semenov together with Alexander Kulakov examined preschool office "Hand bell" of lyceum Elektrogorsk. Capital repairs in establishment are complete for 54%. In building still it is necessary to finish the device of floors, to repair a blind area, a socle and entrance group, to lay out brick walls, to mount partitions, to execute internal finishing of rooms, to mount engineering networks and to arrange well the territory. "Repair kindergartens – important and necessary procedure which provides...