The most part of the equipment for Irkutsk polymer plant is delivered to Ust-Kut

@RUPEC
Show original
The Irkutsk oil company received 95% of the equipment which is necessary for completion of constructions Irkutsk polymer plant, the director of IZP Vaulina Helena on International Baikal risk forum (BRIEF) on Friday. "95% of the equipment are delivered to a platform, 77%" are thus mounted already — she told (the quote on information agency "Interfaks"). Vaulina Helena confirmed that start of plant is planned for December, 2024. In recent weeks in mass media there was different information on terms of start of plant in operation. General director Ginzburg Yakov at a forum to Tyumen confirmed with INK input in 2024, however is later with reference to...