Court rejected the large claim to the Belgorod SRO under article 60.1 GRK as the unfinished advance payment is not a responsibility measure

@
Show original
To download the original of the image Resolving dispute with participation of ASSOCIATION "SELF-REGULATORY BODY "STROITELI BELGORODSKOY OBLASTI" (ASSOCIATION "SELF-REGULATORY BODY "STROITELI BELGORODSKOY OBLASTI", CPO-C-012-04062009), court emphasized that return of unfinished advance payment is not included in a disposition of article 60.1 Federal law of the Russian Federation of 29 December 2004 No. 190-FZ "On the City Planning Code of the Russian Federation". With details – our voluntary expert from Belgorod. *** In December, 2021 LLC "BUILDING COMPANY "INVESTPROMELIT" signed with Regional State Budgetary Institution <2> "Management of capital construction of the Belgorod region" the state contract on performance...