The program of increase of reliability on power facilities continued in Moscow Region

Show original
The Moscow regional power MINISTRY POWER ENGINEERING SPECIALISTS OF THE MOSCOW REGION carries out the program of increase of reliability of power supply inhabitants of the region. Now the staff of companies "Mosoblenergo" finished works on 248 power objects, such as substations and power lines. Until the end of October of the current year it is planned to carry out works on 31 objects according to this program. Within the program make replacement of support and wires on power lines. At present replaced 493 support from 567 planned, and also 71 km of wires from 81 km. Most of all wires replaced in Ramenskoye (19,9 km)...