roadwork within the Safe Qualitative <4> Roads </4> project] procee
Today within the Safe Qualitative <4> Roads 4> program the following is executed: On Halturin's streets and Maklinsky work are already complete. On Turetskaya Street pass actions for laying of the second layer of asphalt. On the street of Kirov works on dismantling of an onboard stone are performed. Today works on curbstone installation on the sidewalk, and also the device of a sandy and crushed-stone layer under the sidewalk are performed. Arrangement of crossings and adjunctions is carried out. Also on 1st Aerodromnoy Street earthwork under the border device is performed. The onboard stone is established. On...