The deputy mayor Ulan-Ude – about a heating main No. 3: "The deadline have to meet"

Show original
Here some months as inhabitants Railway and parts Sovetsky rayon the cities remained without hot water. The reason – heating main No. 3 reconstruction. It is the large-scale project thanks to which a number of problems – from municipal to ecological is removed. The deputy mayor - the chairman of committee on construction Tatyana Matveev told Ulan-Ude about how affairs on object are today. - At us according to the project the point "And" is on CHPP-1. That is we crash into the existing pipeline. There has to be an installation of the largest on diameter of a pipe – 920 mm. From this point system...