Four of six coppers at CHPP Riddera plan to start next month

Show original
3097 according to Akim's deputy of Province of East Kazakhstan Bakytzhan Kakenkadzhievich Bayakhmetov, repair work on Ridder combined heat and power plants go strictly according to the drawn-up plan, the press service of akimat of area transfers. "By September 20 of the current year we plan to finish repair work on four coppers from six available, – Bakytzhan Kakenkadzhievich Bayakhmetov noted. – These are three coppers of average pressure and one – a high pressure. Today readiness of the first and second coppers is made by 44%. Repair two more coppers will come to the end a little later. That is, one will be ready to work in the October, the second – in November". At the beginning of a heating season, till January, with...