The new heating main at Minayevsky Bridge in Ulyanovsk is almost ready

Show original
Transfer of the heathighway along Minayevsky Bridge in Ulyanovsk is executed for 95 percent. About it today, on July 21, 2023, the deputy chief of MUNICIPAL STATE-FINANCED INSTITUTION "STROYZAKAZCHIK" Shamil Vakhitov reported. It is a question of installation and a reorganization of engineering communications cold water supply, pressure head sewerages, the gas pipeline, a heat supply, high-voltage electric cables and communication networks. "New pipelines are already laid and connected on support. The jack is also made, it will install in the next. Besides, experts finish arrangement of pavilion of adjustment" — Shamil Vakhitov added. Connection of the new...