On the nuclear Yakutia ice breaker shipped steam-turbine installation

@
Show original
Specialists of JOINT-STOCK COMPANY "BALTIYSKY FACTORY" (enters OSK) finished loading of steam-turbine installation of the left board on the third serial nuclear ice breaker of the Yakutia project 22220. Loading of technical training college with a lump about 300 tons was made by parts: at first on order loaded the generator and the condenser, then - the turbine weighing 140 tons. The equipment was delivered and shipped on the ice breaker with help the floating Demag crane. After installation of products on regular places specialists of JOINT-STOCK COMPANY "BALTIYSKY FACTORY" started assembly and installation of equipment. Steam-turbine installation which part two main turbogenerators are...