To Scotland it is planned to realize 6 projects which will allow to increase the total power of hydroheat-sink power industry of United Kingdom by 4,9 GW, including: Construction pumped storage power plant of Red John with a power of 450 MWt in

Show original
To Scotland it is planned to realize 6 projects which will allow to increase the total power of hydroheat-sink power industry of United Kingdom by 4,9 GW, including: Construction pumped storage power plant of Red John with a power of 450 MWt in a generating mode on the Northern Highlands (the northwest Scotland). Commissioning of station is planned in 2027 Construction pumped storage power plant of Glenmuckloch with a power of 210 MWt in a generating mode in the District of Dumfries and Galloway (the southern part Scotland). Commissioning of pumped storage power plant is planned in 2029. Re-equipment of operating hydroelectric power station of Cruachan with a power of 440 MWt in the district Argayl-and-Byyut...