On the Magadan combined heat and power plant delivered coal more than a half for a new heating season

@RuNews24
Show original
It is a question about 105,6 thousand tons. In Magadan on local CHPP <0> of PAO "Magadanenergo" delivered 105, 6 thousand tons. It is necessary for a heating season. This figure – only 58% of all amounts of works. In total combined heat and power plant need 253 thousand tons of coal. Such information published in MagadanMedia with reference to the organization. "We last year delivered 50 thousand tons of coal. It is connected with repair a fuel feeding path at power plant. During performance of work coal cannot be delivered freely already", about – general director noted PUBLIC JOINT-STOCK COMPANY "MAGADANENERGO" Vladimir Milotvorsky. In May the vessel "Omolon" brought two...