Company Ariadni Interconnection * successfully finished laying and installation of all underwater C – one of important milestones in realization construction projects HVDC of connection of 500 kV Crete-Attica, which purpose

Show original
Company Ariadni Interconnection * successfully finished laying and installation of all underwater C – one of important milestones in realization construction projects HVDC of connection of 500 kV Crete-Attica which purpose is connection of a power supply system of the lake of Crete with a power supply system Region of Attica (southeast area of Region of Central Greece). From the moment of signing of contracts according to construction project connections Kritattika in June, 2020 of Ariadni Interconnection laid in total about 1350 km of power and fiber-optical cables. Depth of laying C on a bottom of the Aegean Sea reached 1200 m, and the weight of cables...