The Finnish TVO plans to restart at the end of December the third power unit of EPR-1600 the nuclear power plant "Olkiluoto"

Show original
The earliest date of renewal electricity generation on the third power unit of EPR-1600 the nuclear power plant "Olkiluoto" was postponed for two weeks ago - for December 25 therefore regular electricity generation will begin in February, 2023, company reported Industrial Power COR "Teollisuuden Voima Oyj". In updated information of TVO it is said that "investigation of damage of pumps of feedwater on the third power unit of the nuclear power plant "Olkiluoto" passed into a closing stage", having added that, according to consortium of suppliers of Areva-Siemens station, concerning the schedule remain uncertainty. "Proceeds...
Analysis
×
TVO
Main activity:Production and distribution of the electric power, gas and water
Manufactured by:Orano