Courts: acceptance uncoordinated doprabot without objections not an occasion to collect their payment from the state customer

@zakupki-portal.ru_novosti_
Show original
The parties coordinated works on improvement. The contractor executed the main volume, but showed to acceptance also dopraboty. The customer signed acts without remarks, but dopraboty did not pay. The first instance and the cassation did not collect money: - performance doprabot without the change in price does not oblige the customer them to pay contracts. The contractor of work did not coordinate. It could suspend execution, but assumed risks of possible consequences; - that dopraboty executed, reported about it to the customer and reached the general result on contract, not an occasion to collect payment. Does not matter also that...