School on Vereshchagin Street in Sevastopol will hand over in the second half of the year 2023

Show original
Construction schools on Vereshchagin Street in Sevastopol were frozen for half a year. During productions works the additional researches which result there was a detection of discrepancy of group of soil were carried out. "In this regard carrying out additional calculations and updating of budget documentation on the ditch device was required. Besides, project cost recalculation taking into account a rise in price of the prices of construction materials was made. Because of the arisen difficulties it was necessary to stop works for six months. Today all these difficulties behind, works are conducted in the full...