Ministry of Energy: In thermal power plants and main lines there is a thorough training by autumn winter season

@
Show original
By the enterprises of the power sphere Uzbekistan for July 1, 2022 it is ahead of schedule works on preparation of thermal power plants by autumn winter season. Only according to the schedule of capital and current repairs on thermal power plant 54 power units, 31 kotloagregat, 6 turbogenerators, 8 steam-gas installations are repaired. On power transformers of 35-110-220-500 kV it is performed 65 current and capital repair work, capital and current repair 290 switches, dividers, measuring transformers, devices of relay protection and automatic equipment of 35-110-220-500 quarter is carried out. Repair and...