The Finnish TVO plans on March 15 connection to the power supply network of the third power unit of the nuclear power plant "Olkiluoto"

@Atomnaja energija 2.0
Show original
Tests on commissioning of the third power unit of the nuclear power plant "Olikluoto" take place successfully, and connection to a network is expected on March 15, company reported Industrial Power COR "Teollisuuden Voima Oyj". This fifth nuclear power unit Finland reached the first criticality in December and now passes commissioning tests before synchronization with a network. Company TVO declared that it "already tested development of the first megawatts in an electric network". According to the last production forecast of companies, commissioning tests of the generating switch had to be carried out both in manual, and in...
Analysis
×
TVO
Main activity:Production and distribution of the electric power, gas and water
Manufactured by:Orano