On nuclear power plant EB-1 Ruppur to Bangladesh GTsT welding] is complet

@ENERGON'JuS
Show original
On February 24 on a platform of a construction of the nuclear power plant "Ruppur" in Bangladesh (the general designer and a general contractor — the Engineering division of State corporation "Rosatom") in a reactor building of the first power unit is complete one of the most important stages of construction – main circulating pipeline (MCP) welding. Installation of GTsT began on December 15, 2021, within 72 days welding, heat treatment, nondestructive control was carried out and these works are handed over to the customer. Works on a naplavka of austenitic stainless steel on internal welded seams which becomes protection are now conducted...