There are 100 km in the Baltic Sea! MGP Baltic Pipe chronicles for July 13-16

@Neftegaz.RU
Show original
Construction is conducted on all sites of the difficult project Moscow, 16 Jul - Neftegaz.RU news agency. Construction the Baltic Pipe main gas pipeline (MGP) actively goes by land and by sea: in the Baltic Sea construction is conducted by 2 pipelaying vessels, on land in Poland work also is humming, it seems, there are motions and on the Danish overland site. Data of the MarineTraffic, VesselFinder and MyShipTracking services, and also messages of the operator of the project and its participants testify to it. Baltic Sea. Castorone Castorone, the most powerful pipe layer of companies Saipem which is the contractor on...