Dispute because of easements stopped construction the gas pipeline to Volgodonsk

Show original
Dissatisfied owners of land from Zimovniki district the Active phase of construction a pipeline crossing point between Dubovsky and Volgodonsk did not begin because of the farmlands not signed by owners on which there will pass the pipe, special encumbrances or easements which allow construction works and gas pipeline operation on their sites. The situation was so serious that last week Volgodonsk "daughters" visited the representative of head office of the customer of constructions PUBLIC JOINT-STOCK COMPANY "GAZPROM" "PUBLIC JOINT-STOCK COMPANY "GAZPROM" investment" and the staff of the Rostov branch of companies. To convince peasants...