Kraszhilfond transferred completion date of constructions houses in the area "Solonetzic soils-2"

@NKK
Show original
Prosecutor's office carried out an inspection of the actual course of constructions a house No. 10 in the area "Solonetzic soils-2" which conducts Kraszhilfond. The date of commissioning is postponed since June 30 for September 30, 2021. Check revealed that on object there is no construction equipment and...