The Atommash plant "ATOMMASH" started production reactor installation for the power unit No. 2 of Kursk AES-2

@Armtorg.ru
Show original
At Atommash plant "ATOMMASH" began production reactor installation for further deliveries on a platform of the power unit No. 2 of Kursk AES-2. So, at the enterprise at different fabrication stages there is a case of the nuclear VVER-TOI reactor and a set of steam generators. Experts prepare the feedwell of an active zone of the reactor for an anticorrosive naplavka. The feedwell of a zone of branch pipes and flange pass machining. branch pipes are made by SAOZ. Today "ATOMMASH" carries out mechanical tests of bottoms the reactor. Besides, production the steam generator case which consists of four comes to the end...