Two wind farms will construct in Anadyr district this winter (Chukotka Autonomous District)

@ADVIS.RU
Show original
In two settlements Anadyr district at the end of it and at the beginning of 2021 have to earn wind farms. Renewables will partially replace generating capacities in the settlement Beringovsky and the village Ust-Belaya, reports Chukotka news agency with reference to department of industrial policy Chukotka Autonomous District. In each settlement specialists of LLC "Company Nord Marin" mounted on two sets of wind generators with a power of 450 kW. In Beringovskom constructed two power lines of 0,4 kV and 6 kV with a general extent of 550 meters, commissioning is carried out. "Input in...