In Republic of Crimea the Saksky combined heat and power plant reached full capacity

Show original
The station started giving out the electric power in a power supply system of the peninsula Simferopol, on March 4. information agency "ITAR-TASS". The Saksky combined heat and power plant in Republic of Crimea reached full capacity and started giving out the electric power in a peninsula power supply system, told to journalists on Wednesday in the press service of companies to "KRYMTETS" operating object. 3 Material Earlier in October on a site of Ministry of Energy of the Russian Federation following the results of exit meeting of the Deputy Minister of Energy Andrey Cherezov were reported that the constructed Saksky combined heat and power plant which Republic of Crimea till summer of 2019 had to connect to networks, still did not receive allowing documents for input in...