In 2019 of Federal public institution Uprdor "Vilyuy" A-331 "Vilyuy" and R-504 "Kolyma", and also 1364 running meters of artificial constructions put into operation 167 km of federal highways. In total on the route "Vilyuy" 83 km of highways are repaired, constructed and reconstructed. The asphalt concrete covering on a 188-kilometer site from Yakutsk to the village Berdigestyakh of the Mountain area is thus provided. Opening of the largest in scales Sakha (Yakutia) Republic the bridge crossing through the Markha River on the 756th km of the route "Vilyuy" became the main event of 2019. Length of the main bridge makes 560 items of m and two small bridges – 55 and 34 items of m...