PUBLIC JOINT-STOCK COMPANY "T PLUS" began a conclusion from combined heat and power plant operation in Yekaterinburg

@Pravda UrFO
Show original
Consumers will transfer to CHPP Akademicheskaya of PUBLIC JOINT-STOCK COMPANY "T PLUS" there began the project of optimization of thermal knot of southwest part Yekaterinburg. Its realization will allow to refuse use of inefficient CHPP-19. As the press service of companies reports, construction by the first of two pump stations in the territory adjacent to CHPP Akademicheskaya is already begun. The cost of all project will make 1,2 billion rubles. "After optimization company will expand opportunities for connection of new consumers, in particular, areas of perspective building – Academic, the Wide small river, UNTs...
Analysis
×
PUBLIC JOINT-STOCK COMPANY "T PLUS"
Main activity:Production and distribution of the electric power, gas and water
51