The Dzerzhinsk thermal networks of the Nizhny Novgorod branch PUBLIC JOINT-STOCK COMPANY "T PLUS" reconstruct a heating main on Petrishchev St.

Show original

the Dzerzhinsk thermal networks of the Nizhny Novgorod branch PUBLIC JOINT-STOCK COMPANY "T PLUS" reconstruct the main heating main on Petrishchev St. more than 1,2 km long. The press service of companies reported about it on August 14, 2018.

"The project of modernization of heating mains with application the isolated pipelines provides previously replacement of a site of the high-level thermal networks from a thermal chamber No. 2 to a thermal chamber No. 132I. Use of modern pipes in polyurethane foam (PPU) of isolation allows to increase the term of their operation and to reduce heatlosses", - it is noted in information.

For minimization of time of shutdown hot water supplies consumers of GVS of work are divided by

into some stages. The first stage will pass without GVS shutdown. For this purpose the Dzerzhinsk thermal networks in 2017 established partitioning shutoff valves in TK-132A. Works on technical rearmament started on August 13 and will last until the end of September. "Work will be carried out large-scale as the pipeline of big diameter of Du=500 of mm and 1276 running meters long changes. The purpose of reconstruction of thermal networks – to provide inhabitants Dzerzhinsk with a reliable and uninterrupted heat supply throughout all forthcoming heating season", – the deputy technical director of DTS Anatoly Verin noted.