In Volgograd residents of the emergency house did not receive the promised apartments

@Rossijskaja gazeta
Show original
Because of sluggishness of the contractor people cannot become populated some months to the new house
Stepantsov' Family from the Ancient settlement since 2009 expects when them will move from a dangerous structure to the new house. And after all and in the program included, and the three-storyed house to 30 apartments started building, and had to put a new building in operation even last fall. But people still huddle in old tumble-down houses because the contractor broke all terms.

- We moved here from Uryupinsk 15 years ago, bought the apartment. But, in fact, it not capital housing, and simply two cars, put one on another and laid over by a brick, - is told by Stepantsova Tatyana. - In such temporary barracks there lived the workers constructing the Moscow track. Now all wooden designs recognized as normal houses. And all of them rotted through, in a hole floor. When the washing machine works, all room shivers. Wires are hanging by a thread.

Stepantsov suggested to get over for a while in maneuverable fund, but they disagreed. Were afraid that then about them in general will forget.

the New house had to build by September 30 of last year. As the contractor the Moscow firm which does not have due experience acted. However at the auction she offered the best price. Earlier on it there were complaints to Tver, Kostroma and Tula where work was conducted so slowly. Experts stroykomiteta even addressed in Department of the Federal Antimonopoly Service on Volgograd region with the offer to bring the company in the register of unfair suppliers. However anti-monopolists refused. However, now this decision will be challenged in arbitration court.

- In activity of the contractor revealed violations. It involved foreign workers without allowing documents. Administrative production concerning the director of society who ignores our agenda is excited, - the prosecutor reported Gorodishchensky rayon Shilov Aleksey.

By the way, Asian workers on building are still. At the sight of us with cameras they scaredly wave hands and shout: "It is not necessary!"

Now Muscovites forced to take on a subcontract other organization possessing sufficient construction capacities. By February 10 the building has to be ready to settling. However at first it is necessary to correct the defects allowed by predecessors.

- Inspection revealed p that some works were conducted at a negative temperature that cannot be done categorically. The heater became useless. All this should be eliminated, - the deputy head of management of capital construction of area Sedov Vladimir noted.

according to officials, more in the region there are no houses, with violation of terms built according to the resettlement program. However activists of People's Front for Russia claim that similar problems are in the village Raygorod Svetly Yar district and in gorod Krasnoslobodsk.

Comment

Kuznetsova Svetlana, chairman regional COMMITTEE STROITELSTVA:

- the Customer the settlement administration the Ancient settlement which had to control process acts. In July it became clear that builders do not meet the deadline. By November there was a lag for four months. The cost of construction of this house made 44,5 million rubles. However the settlement administration prolonged term and went for 10 percent rise in price, to 48 million. The conclusion of the additional agreement is illegal because the date of performance is an essential condition. And essential conditions do not change. Because of this object to us can suspend financing and apply sanctions to the region.

can actually Solve Meanwhile a problem of emergency houses without uniform brick. There is enough paper. Wonderful transformation happened in Volgograd to the nine-storey building on Triumfalnaya Street, 6. As the press service of the Commissioner for Human Rights in area reports, in April, 2012 the house recognized subject to demolition. However at decision-making forgot to receive the decision about technical condition of a structure. Incomplete materials the city hall returned to administration Krasnooktyabrsky rayon. The next four years officials did not come back to this question. Only when at one of residents the patience (likely, was frightened that earlier the same happens to a bearing wall) burst, it appealed to court. And the city hall obliged to be defined. As a result of February 17, 2016 ADMINISTRATION OF VOLGOGRAD recognized rooms "suitable for accommodation". Undoubtedly, this experience needs to be extended to other spheres of life more widely. It is worth recognizing patients recovered - and the budget of health care will be more whole, and the statistics of eyes will please. To issue the broken roads as modern highways - again economy. And everything will be smooth. On paper.