On obtaining the construction license to Leningrad region 156 days - And 17 procedures on the average are necessary

Show original

Photo documents from a site topwar.ru For obtaining the construction license to Leningrad region on the average the builder has to spend

And 17 procedures 156 days. It on Monday was declared by the chairman of State board Stroitel supervision and state examination Leningrad region Shibaev Vyacheslav, the correspondent of ABN reports. <= "more-370969">

For obtaining all permissions builders pass span id approximately through 17 procedures. In Government of Leningrad region declared that these figures have to be less. It is supposed that obtaining permissions has to be carried out in 85 days due to passing of four procedures.

we Will note p, in the territory of Leningrad region 75 thousand are registered. contracts of share construction. In total in area more than 600 inhabited objects are under construction. They are built by over 100 companies.