Building "got stuck in a bog". The term of delivery of schools in the Irkutsk residential district Anniversary can break the second time
Here expectation, and here reality. in the Anniversary residential district Irkutsk from budgets allocated huge money for new school — billion 700 million rubles. Builders had to hand over object still at the end of last year. But while, according to the contractor, for 75 percent only the first block is ready. On the second now do the base, the third did not start yet. And all such blocks has to be seven. Place chose marshy, and building quickly got stuck. After in the spring of the 21st year contract company "won SPMK-7 ″, the contractor started making at once changes to the project. The tape base offered...