​ "Daughter" of "Rosenergoatom" postponed commissioning to a year data-centers in Innopolis for 5 billion rubles

@Biznes Online
Show original
The affiliated company "Rosenergoatom" of JSC Atomdata Innopolis will construct in the IT city data-processing center (TsOD). Commissioning planned for December 31, 2023 instead of planned before November of the 2022nd. The cost of constructions — 5,3 billion rubles, 2 billion from which will leave on the equipment. The corresponding tender appeared on a portal of government purchases. TsOD will be calculated on 2 thousand racks. First of all will establish an IT equipment half, installation remained, allegedly, will occur after 2023. it became known of plans of constructions in the 2020th. In December of the same year concluded...