SUENCO finished the next stage of reconstruction of PS "Belozerskaya" on August 3, 2022 12:00

@Pravda UrFO
Show original
Power engineering specialists of SUENCO within investment programs provided 2022 high level of fire safety and explosion safety of key substation Belozersky rayon – 110/35/10 kV of PS "Belozerskaya". Within reconstruction the outdated equipment of the open distributing device of 110 kV is replaced with substations "Belozerskaya". New high-voltage gas-insulated switches of domestic productions in case of an emergency situation disconnect the damaged site of a network in 0,05 seconds, thus there are no harmful emissions in environment. Federal Service for Ecological, Technological and Nuclear Supervision already gave out permission to the admission...