For design and construction Gorodetsky's additional chamber of the water-engineering system allocated 21,8 billion rub

@Morskie vesti Rossii
Show original
At the request of Federal Agency of Maritime and River Transport, competition on design and construction an additional chamber (lock) No. 15-A and an approach ship canal as a part of Gorodetsky of the water-engineering system is announced. The head of Agencies reported about it Andrey Lavrishchev. Initial (maximum) price of the contract - 21,8 billion rubles. Works have to be performed by the contractor during 2024. The new lock will adjoin a chamber No. 15 and will allow vessels to overcome a present threshold of a lock - the main limiting factor in a water-engineering system alignment. Also dredging works will be carried out on below...