Year will occupy repair LNG plant to Norway after a strong fire

@Neft' i Kapital
Show original
She notes that besides the damages caused by a fire on an air inlet of one of five power turbines, a large amount of sea water at suppression damaged electric equipment and cables. The amount of works on elimination of this connected damage is considered the most considerable, and duration ostanova will depend on the term of deliveries the necessary equipment. Process will be influenced also by restrictions in connection with Koronavirus. At the same time Equinor intends to use a plant stop for carrying out the planned works planned for 2021. The Hammerfest LNG plant on Melkoya island, notes...