PUBLIC JOINT-STOCK COMPANY "ENEL RUSSIA" delivered the first party of the capital equipment for the Azov wind farm

Show original
Rostov-on-Don. May 15. INTERFAX-SOUTH - PUBLIC JOINT-STOCK COMPANY "ENEL RUSSIA" delivered on under construction in Rostov Region the Azov wind farm (VES) the first sets of towers and the naves, necessary for constructions wind turbines, is spoken in the message of companies. The first set of towers consists of three sections the longest of which reaches nearly 30 meters and 79 tons weigh, and their gross weight makes nearly 200 tons. In total sets will be 26 - such is total of wind turbines of the Azov VES. Besides a set of towers, the first naves were delivered to a building site. In the next few days arrival is expected...
Analysis
×
PJSC Enel Russia
Main activity:Production and distribution of the electric power, gas and water
2
Siemens AG
Main activity:Communication and IT