The first stage of substation for a hothouse complex is entered into Tula Region

@Interfax-Russia
Show original
Tula. February 20. JSC "Interfaks-Centre" - the First stage of substation of 220 kV "Hothouse" is put into operation in Shchyokino district Tula Region, the press service of JOINT-STOCK COMPANY "SISTEMNY OPERATOR YEDINOY ENERGETICHESKOY SISTEMY" ("The system operator of EEC") "Reported. During constructions on its platform substation buildings are built and constructions, one 80 MVA power transformer is installed, the open distributing device of 220 kV is mounted. Besides calling on PS of 220 kV "Hothouse" from Shchekinsky state district power station with tap on PS "Yasnopolyanskaya" with education two power lines" are constructed, - is spoken in the message. Specialists of JOINT-STOCK COMPANY "SISTEMNY OPERATOR YEDINOY ENERGETICHESKOY SISTEMY"...
Analysis
×
CJSC "Interfaks-Tsentr"
Main activity:Science and education
2
JOINT-STOCK COMPANY "SO YEES"
Main activity:Production and distribution of the electric power, gas and water
20