More than a half of a metalwork of OF "Inaglinskaya-2" are mounted!
Today our builders mounted 60% of a metalwork of the main case, more than 20% of processing equipment are installed. Implementation of the project goes according to the schedule, start of the first stage of OF "Inaglinskaya-2" is planned for May 9, 2020. OF "Inaglinskaya-2" is created in two turns 6 million tons of coal a year. In close proximity to factory the necessary infrastructure — loading station, commodity and material warehouses, railway access roads, power lines and substations, administrative and household complexes will be created. Construction the concentrating...