New and Sverdlovsk combined heat and power plant will stop almost for two weeks because of preparation for winter

Show original
informational and analytical agency "UralBusinessKonsalting", Yekaterinburg, 16.08.2019. New and Sverdlovsk combined heat and power plant will stop because of preparation for the winter period. Hot water supply Berezovsky's consumers will be completely limited from August 16 to August 28. The press service of Sverdlovsk branch PUBLIC JOINT-STOCK COMPANY "T PLUS". "From August 16 to August 28 will pass the current repair gas-distributing point, the gas pipeline of a high pressure, gas flues of coppers, replacement and repair not switched-off fittings...