For 3,5 years the Kaliningrad power engineering specialists constructed more than 388 km of power lines

Show original
For 3,5 years the Kaliningrad power engineering specialists constructed more than 388 km of power lines that corresponds to distance from Kaliningrad to Vilnius. Yutkin Kirill, director general "PUBLIC JOINT-STOCK COMPANY "ROSSETI" Amber" at a meeting with representatives of regional business community which took place in KALININGRADSKAYA TPP on August 15, 2019...

Full article is available at its source

Go to full article
Open the Connections Tree and see if PJSC Rosseti and are connected in any way
Try it

Sign up for more features!

Get full access to news analytics for free and without ads.

Article analysis

×
Persons
in this article
Yutkin Kirill
Organizations
in this article
PJSC Rosseti
Main activity:Production and distribution of the electric power, gas and water