On the route R-254 "Irtysh" in Kurgan Region laying of the top layer of asphalt] begin

@DorInfo
Show original
In Vargashi district Kurgan Region on federal road R-254 "Irtysh" the contractor starts laying of the top layer of asphalt. The press service reports JOINT-STOCK COMPANY "URALAUTODOR" on Friday, August 16. Capital repairs a site with 297th on the 309th km of the route "Irtysh" began last year. During this time road builders carried out works on restoration and fixing of an axis of the route and piketazha, to expansion of a road bed with removal of soil and vegetable soil, to strengthening of roadsides and dumping of slopes by sandy loam. Now the bottom layer of asphalt concrete is laid on 10 of 12 km...