The house SU-155 on Khromov will be leased in June, 2017

@TIA
Show original
on March 06, 2017 15:59
Author: TIA

on March 6 at operational meeting of the governor Igor Mikhaylovich Rudenya discussed construction of seven houses Su-155 with members of Government of Tver region. The schedule of works on two objects on streets Khromova and Osnabryukskaya was not observed, however now, according to the director general LLC "ROAD-BUILDING COOPERATIVE-5" Kondratyev Youri, lag is liquidated. And as a whole, it will not be reflected in terms of delivery of objects as the press service of Government of Tver region reports.

on March 6 at operational meeting of the governor Igor Mikhaylovich Rudenya discussed construction of seven houses Su-155 with members of Government of Tver region. The schedule of works on two objects on streets Khromova and Osnabryukskaya was not observed, however now, according to the director general LLC "ROAD-BUILDING COOPERATIVE-5" Kondratyev Youri, lag is liquidated. And as a whole, it will not be reflected in terms of delivery of objects as the press service of Government of Tver region reports.

So, in the house No. 29 on Khromov Street at the beginning of April works on arrangement of an external sewer network will begin p. Now there is a preparation for installation of the lift equipment. Case input according to the schedule is planned for August of this year, but the contractor is ready to accelerate rates and to hand over object in June.

On construction of the monolithic block on Osnabryukskaya, 29 recorded lag in installation of the sanitary equipment and finishing. Since March 10 sanitary works, in April – finishing here will begin. Delivery of the case is provided at the end of the current year.

As were reported by the director general of LLC "STROYGRUPP" Troshkin Dimitri, works on all objects of SU-155 which are finished by the company, are conducted within the schedule.

SU-155 Krom, at operational meeting brought up a question of construction of a boiler room in Mamulino-3. Project documentation is in development. The governor reminded of need in short terms to resolve an issue with coordination that in August the boiler room was ready to work. To control all stages of works on a boiler room - from obordovaniye before delivery to Rostekhnadzor - Tver region on ensuring control functions Shaforost Victor is entrusted to the minister.